FOD Project Update |
| |
9th Avenue Garage Expansion (MCFP)
| ||
May 12, 2008 | ||
The 9th Ave Parking Garage Expansion is the addition of a second 1000-car garage east of the existing parking garage located on the corner of 9th Avenue and Medical Center Drive. This garage will occupy the site of an existing university surface parking lot along 9th Avenue. The construction is slated to begin in the summer of 2008 and to be completed in late summer 2009. The alleys adjacent to the project will be resurfaced or replaced, depending on underground conditions. Traffic flow in and around the site will be temporarily interrupted at times as construction and utility work commences. | ||
| ||
| ||
Project Updates | May 7 The contracting team has been selected by public bid process and the contracts awarded. The electrical contractor will begin mobilization soon and be working in the north-south and east-west alleys within the next two weeks. Look for temporary closures of the alleys around the construction site. | |
| ||
Project Status Report | The target date to begin construction is June 9, 2008 after spring quarter Commencement. Look for further detailed information updates as construction begins. | |
| ||
Next Update | We anticipate issuing the next update in mid-July. This will allow us to include pertinent information from the early construction excavations and below grade work. | |
| ||
University Contacts | You can contact the FOD project manager or construction manager if you have questions or comments: Charlie Conner, Project Manager, 292-3341, conner.26@ osu.edu Glenn Gerhart, Construction Manager, 688-5606, gerhart.1@osu.edu
Glenn will be our primary representative in the field as this project moves into the construction phase. Please direct all construction-related questions/comments to Glenn. | |