| FOD Project Update | |
9th Avenue Garage Expansion Medical Center Facilities Plan (MCFP) Enabling Project | ||
August 11, 2008 | ||
| ||
| ||
Project Updates |
Summer Overview:
June Contractors Mobilized Dugan & Myers Construction – general trades and lead contractor Aggressive Mechanical Services – plumbing, fire protection contractor J.A. Guy, Inc. – HVAC contractor Accurate Electric – electrical contractor
July Mass site excavation was completed and work progressed on the building foundation systems. The south alley utilities were re-routed and abandoned as required. The south alley was closed to through traffic until the alley surface is replaced later in the project.
August 9th Avenue, in front of the site, will be reduced in width to allow installation of a tower crane at the front of the site. Two-lane traffic will be maintained on 9th Avenue. As part of an approved Maintenance of Traffic (MOT) plan, new concrete barriers and fencing will be installed along 9th Avenue as an additional traffic safety measure.
September 9th Avenue to be closed to erect tower crane on Sept.13-14. Signage and MOT plan prepared by Transportation & Parking and Sgt. Bissett. Alternate routes provided along King Avenue to Cannon Drive.
| |
Next update | The next update is anticipated during the next quarter of construction. This will allow us to include pertinent project update information. | |
Contact | For questions or comments, please contact Charlie Conner, Project Manager, 292-3341, conner.26@ osu.edu; or, Glenn Gerhart, Construction Manager, 688‑5606, gerhart.1@osu.edu. | |